What it costs to connect to sewer, utility by utility
In Florida's Indian River Lagoon program area, the published septic-to-sewer cost runs from about $7,000 to $25,000 per home. Indian River County quotes $7,000 to $15,000 for gravity and $15,000 to $25,000 for a pump connection, Fort Pierce lists $10,395, and Vero Beach averages $15,000 to $17,000. Many utilities publish no total.

The table
Every figure below comes from the utility's own fee schedule or program page, or from dated news quoting the utility. "Not published" means we could not find a figure on November 1, 2026; the phone is the one to call. Read the source column before you plan around a number: some fees are a few years old.
| Utility | Area served | Fees | Owner total | Help or plan | Source |
|---|---|---|---|---|---|
| Palm Bay Utilities | Palm Bay | Line extension $2,370.40, sewer capital charge $3,300, deposit $100: $5,770.40 on an 80 ft lot | "$12,000 or more" (city) | Fees of about $5,670.40 waived for eligible sewer-available properties; payment plan up to 5 years for owner-occupied homes. (321) 952-3420 | City pages, Apr 2026, Oct 2025 and Jul 2025 captures |
| City of Melbourne | Melbourne utility area | Sewer impact fee $4,165; connect fee $100 | Not published | Not published; county Quick Connect grant. (321) 608-7100 | City rate table, read Nov 1, 2026 (no date shown) |
| City of Cocoa | Cocoa utility area | Sewer impact fee $1,875 per ERC; sewer force main fee $1,450 per ERC | Not published | Not published; county Quick Connect grant. (321) 433-8400 | City Schedule B, updated Oct 2026 |
| City of Titusville | Titusville | Not published | Not published | Ask the city. (321) 567-3866 | Not published |
| City of Rockledge | Rockledge | Not published | Not published | Ask the city. (321) 221-7540 | Not published |
| City of Cocoa Beach | Cocoa Beach | New sewer installation $2,200 per single-family unit in city ($3,300 outside) | Not published | County Quick Connect grant. (321) 868-3321 | City water reclamation fees page, read Nov 1, 2026 |
| Brevard County Utility Services | Unincorporated Brevard, including county sewer project zones | Not published | Not published | Quick Connect grant can pay the connection fee straight to the county. (321) 633-2091 | County grants page, Nov 2025 capture |
| City of West Melbourne | West Melbourne | Not published | Not published | Ask the city. (321) 837-7750 | Not published |
| Indian River County Utilities | North, central and south county service zones | Sewer service connection $3,835 (single family); sewer impact fee $2,624 per ERU | $7,000 to $15,000 gravity; $15,000 to $25,000 low pressure (county) | Up to $15,000 announced, not open yet. 772-226-1832 | Rate booklet, Jan 1, 2025; WQCS, Aug 18, 2026; county program site, Nov 1, 2026 |
| City of Vero Beach (STEP) | City utility area, mainland and island | Impact fee $3,390 (credited by the 2024 help program) | Average $15,000 mainland, $17,000 island (utilities director) | Clean Water Coalition: qualifying owners pay $5,400 over about 10 years. City water and sewer 772-978-5220 | Vero Beach 32963, Jul 10, 2025; Indian River Guardian, Aug 3, 2024 |
| Fort Pierce Utilities Authority (LPS) | Fort Pierce area expansion neighborhoods | Not itemized | $10,395 single-family; duplex $14,855 or $20,790 | Financing available (terms not published); grant toward about half the cost for at least 38 homes (tentative). 772-466-1600 | FPUA presentation, May 7, 2025; WQCS, Feb 24, 2026 |
| St. Lucie County (North Hutchinson Island) | About 530 homes in four island neighborhoods | Current fees not published; $3,200 connection fee reported earlier | $10,000 or more per home (WPTV, no date shown) | 2022 plan: $535 to $817 a year for 20 years (TCPalm). (772) 462-1150 | County project page, Oct 2026 capture; TCPalm, May 10, 2022 |
| Utilities Commission of New Smyrna Beach | New Smyrna Beach | Not published | Not published | Ask the utility. 386-427-1361 | Not published |
| City of Edgewater | Edgewater | Not published | Not published | Ask the city. 386-424-2400 | Not published |
| Oak Hill / Volusia County | Oak Hill (county-run sewer) | Not published | Not published | Ask the county. 386-736-5971 | Not published |
| Port St. Lucie (outside the area, for comparison) | Port St. Lucie | $8,258 conversion, wastewater only | $8,258; city supplies materials and labor to the street pipe | $67.90 a month at 0% for 10 years. 772-873-6400 | City fact sheet, as of Oct 1, 2025 |
Notes on the table:
- Palm Bay: the fee waiver is described on the city's mandatory connection page (October 2025 capture) for eligible properties where sewer is available; the April 2026 service page lists the fees and payment plans without mentioning it. Ask which applies to you.
- Vero Beach: the city's online fee sheet still shows a $2,290 residential sewer impact fee, effective 2010. The help program in 2024 credited $3,390. Ask the city for the current figure.
- Fort Pierce: FPUA says several factors go into each estimate; the $10,395 is its single-family price from May 2025.
- North Hutchinson Island: the county's project page (October 2026 capture) gives no costs. The 2022 figures may have changed.
What goes into the bill
A sewer connection is several bills, not one. Ask for each piece in writing.
- Utility fees. The connection or tap fee, an impact or capacity fee, sometimes a line extension fee, and an account deposit. These are the numbers in the table. In Palm Bay they come to $5,770.40 on a standard lot.
- The plumber's line from your house to the street. A Florida licensed plumber connects your house to the sewer lateral or clean-out the utility marks, under a building permit. Palm Bay suggests making this connection before the tank is closed, so you are not without a toilet. Brevard's grant does not pay for plumbing under the house.
- Pumping and closing the septic tank. A licensed septic contractor pumps the tank and fills it in, under a permit from the Florida Department of Health, and an inspector checks it. Palm Bay's pages say tanks are emptied, disabled and filled, not removed. In Brevard, call the health department at (321) 633-2100, option 1. Palm Bay puts a typical tank pump-out at $250 to $400.
- A pump, where gravity will not work. Low pressure (LPS) and STEP systems put a small pump unit in your yard. In Vero Beach the city supplies the pump vault, tank and panel; you pay for installing them.
- Electrical work. A pump needs power. Vero Beach's ordinance makes the owner pay for the wiring from the pump panel to the house panel, done by a licensed electrician.
- Putting the yard back. Driveway, lawn and landscaping repair. Brevard's grant covers restoring them to how they were.

Gravity vs pump connections
Gravity. Waste flows downhill from your house to a sewer main in the street. Nothing to power or maintain at your home. Indian River County estimates $7,000 to $15,000 for the owner.
Pump connections. Where the ground is flat, the water table is high, or the main is a pressure line, your home needs a pump:
- Low pressure sewer (LPS) grinds and pumps your wastewater into a pressure main. Fort Pierce Utilities Authority and Port St. Lucie use it. Indian River County estimates $15,000 to $25,000 for the owner.
- STEP (septic tank effluent pump) keeps a tank in the yard and pumps only the liquid to the sewer. Vero Beach uses it; the city's average was $15,000 on the mainland and $17,000 on the island in 2025.
- Vacuum sewer is planned on North Hutchinson Island, according to St. Lucie County.
A pump connection costs more, and it needs power. FPUA says its crews pump down each low pressure unit after a storm until power is back. Brevard's Quick Connect grant reflects the difference: up to $12,000 for gravity, up to $24,000 for a force main or a connection that needs a pump.

Grants that cut the cost
- Brevard Quick Connect: $1,600 for each pound of nitrogen a year your connection prevents, up to $12,000 for gravity and $24,000 for a force main or pump. It covers connection fees, permits, contract labor, the pump and closing the tank. Approval comes first: email [email protected] or call (321) 633-2016. Details: Brevard sewer connection grant.
- Indian River County Sewer Connection Assistance: up to $15,000 per property announced, for eligible residents where sewer is available. On November 1, 2026 the application portal had not opened. See Indian River County sewer connection help.
- Vero Beach and the Clean Water Coalition: for qualifying homesteaded owners, the 2024 program credited the impact fee, financed the STEP equipment at 0% over 10 years and had donors pay the plumbing and permits. In 2025 owners paid $5,400 over about 10 years. Funding beyond 2025 is not confirmed; call the Economic Opportunities Council of Indian River County at 772-562-4177.
- Fort Pierce (FPUA) and the Indian River Lagoon National Estuary Program: in February 2026 the lagoon council tentatively awarded FPUA over $200,000 to cut the price by about half for at least 38 homes, paid as reimbursement. Ask FPUA at 772-466-1600.
- Palm Bay: the city's fee waiver for eligible properties where sewer is available, described above.
More programs, including SHIP repair money, are on the septic grants hub and the St. Lucie help page.
Does this apply to your home?
The free address check answers in about ten seconds: inside the program area or not, septic or sewer on record, lot size and, in Brevard, a grant estimate.
When you must connect
- State law: when a public sewer becomes available, the owner of a working septic system must connect within 365 days of the utility's written notice (s. 381.00655, F.S.). The same law lets you prepay connection charges in monthly installments over up to two years from the first notice that sewer is coming.
- The 2030 rule: by July 1, 2030, homes on septic in the program area must connect to sewer if it is available, or upgrade to an ENR system (s. 373.469, F.S., as amended in 2026). Read the 2030 law and ENR or sewer.
- Indian River County: a mandatory connection policy gives owners 365 days after notice.
- Palm Bay: owners where sewer is available get one year from the city's written notice, under the November 2023 ordinance.
- Cocoa: Ordinance 03-2025 lets the city council require owners in a city sewer expansion project, such as areas J and K, to connect.
- Vero Beach: connect to the city's STEP system by June 1, 2028, or within one year of a sale or transfer (Ordinance 2024-05).
- Fort Pierce: FPUA says the St. Lucie health department will not permit a replacement septic system where FPUA low pressure sewer is available.
How we built this table
We checked each utility's fee schedule, rate booklet, ordinance or program page on November 1, 2026, and dated news where the utility was quoted. Where a city site blocks automated reading, we used Internet Archive captures and give their dates. We did not estimate, average or add up anyone's numbers: each cell is what the source says, and the date column says how old it is. Fees change, often on October 1 or January 1. If you work for one of these utilities, or you have a newer bill or fee schedule, send it to us through the about page and we will correct the table and note the date.
Not published yet
On November 1, 2026 we could not find a published septic-to-sewer fee or owner total for:
- Brevard County Utility Services, (321) 633-2091
- Titusville, (321) 567-3866
- Rockledge, (321) 221-7540
- West Melbourne, (321) 837-7750
- Utilities Commission of New Smyrna Beach, 386-427-1361
- Edgewater, 386-424-2400
- Oak Hill and Volusia County utilities, 386-736-5971
- Current North Hutchinson Island terms, St. Lucie County Public Utilities, (772) 462-1150
- Owner totals for Melbourne, Cocoa and Cocoa Beach
Ask for the connection fee, impact or capacity fee, deposit and any payment plan in writing, then get a plumbing quote. Run your numbers in the cost calculator.
Ask a licensed septic company that serves your area to quote the connection and closing your tank. The request goes to one licensed company, free and with no obligation.
Your address, your answer
Find out what the 2030 rule means for your home
Type your address to see if it is inside the program area, whether state records show septic or sewer, your lot size and, in Brevard, an estimate of the county grant. Free, about ten seconds.
Questions people ask
How much does it cost to connect to sewer in Brevard?
It depends on your utility. Palm Bay's own fees are $5,770.40 on a standard 80 foot lot, and the city says a full conversion can cost $12,000 or more. Melbourne charges a $4,165 sewer impact fee, Cocoa $1,875 and Cocoa Beach $2,200. Brevard's Quick Connect grant pays up to $12,000, or $24,000 where a pump is needed.
Do I have to pay to abandon my septic tank?
Usually, yes. A licensed septic contractor pumps the tank and fills it in, under a permit from the Florida Department of Health, and an inspector checks it. Palm Bay tells owners to hire that contractor themselves. Brevard's Quick Connect grant counts closing the tank as a covered cost.
Can I pay over time?
Often. Palm Bay offers payment agreements of up to five years for owner-occupied homes, Port St. Lucie spreads $8,258 over 10 years at 0%, and Fort Pierce Utilities Authority says financing is available. Florida law also lets owners prepay connection charges monthly over up to two years from the first notice.
Why do some neighbors pay so much more than others?
The utility fee is the same for everyone, but the plumbing is not. A long run from the house to the street, a pump unit where gravity sewer is not possible, electrical work for that pump, and fixing the yard or driveway all add to the bill. Indian River County's own range is $7,000 to $25,000.
My utility is not in the table. Where do I start?
Call the utility that sends your water bill, or the sewer utility for your street, and ask three things in writing: is sewer available at my property, what are the connection and impact fees, and is there a payment plan or grant. Then get a written quote from a licensed plumber or septic contractor.
Sources
The laws, agency documents and reports this page relies on. Rules and grant amounts change; confirm with your county before you sign anything.
- Service availability: connecting to city sewer (archived April 15, 2026), City of Palm Bay
- Mandatory connection (archived October 28, 2025), City of Palm Bay
- Septic to sewer program: frequently asked questions (archived July 31, 2025), City of Palm Bay
- Utility rate table, City of Melbourne
- Schedule B: miscellaneous rates, fees and charges (updated October 2026), City of Cocoa
- Ordinance No. 03-2025 relating to septic to sewer conversion of project areas J and K, City of Cocoa
- Water reclamation fees, City of Cocoa Beach
- Save Our Indian River Lagoon: homeowner grants (archived November 17, 2025), Brevard County
- Save Our Indian River Lagoon: sewer projects (archived November 17, 2025), Brevard County
- Schedule of water and sewer rates, fees and other charges, effective January 1, 2025, Indian River County Department of Utility Services
- Indian River County to hold workshops on septic to sewer conversion (August 18, 2026), WQCS
- Indian River County Septic to Sewer Program (Sewer Connection Assistance), Indian River County
- Connection charges and impact fees (effective January 1, 2010), City of Vero Beach
- Vero Beach's advanced STEP sewer system to expand to south on island (July 10, 2025), Vero Beach 32963
- Septic to sewer help available for some City of Vero Beach residents (August 3, 2024), Indian River Guardian
- Ordinance No. 2024-05: STEP connection to central sewer by June 1, 2028 or within 1 year of sale, City of Vero Beach
- Septic to sewer program: low pressure sewer (May 7, 2025), Fort Pierce Utilities Authority
- FPUA tentatively awarded over $200,000 for septic to sewer conversions (February 24, 2026), WQCS
- North Hutchinson Island septic removal project (archived October 3, 2026), St. Lucie County
- North Hutchinson Island owners may share in $17 million septic to sewer cost (TCPalm, May 10, 2022), TCPalm via Yahoo News
- Some residents resistant to septic to sewer conversions, WPTV
- Septic to sewer program fact sheet (2025), City of Port St. Lucie Utility Systems
- Section 381.00655, Florida Statutes: connection of existing onsite systems to central sewerage, Florida Legislature
- Section 373.469, Florida Statutes: Indian River Lagoon Protection Program, Florida Legislature
- HB 1417 (2026), chapter 2026-2, Laws of Florida, The Florida Senate
- Public Utilities customer service: contact us (archived October 2, 2026), St. Lucie County
- New Smyrna Beach Utilities, Utilities Commission
- Frequently asked questions, City of Edgewater
- Water Resources and Utilities, Volusia County
Related
What will it cost you? Septic upgrade and sewer calculator
Work out what an ENR septic upgrade or sewer hookup near the Indian River Lagoon costs you after county grants. Ranges by system type, with sources.
ENR upgrade or sewer connection?
Under the 2030 lagoon rule you connect if sewer is available and upgrade to ENR if not. How to tell which applies, side-by-side costs, and when to wait.
Brevard County septic grant and sewer connection grant
Brevard's Save Our Indian River Lagoon pays $6,000 to $20,000 to upgrade a septic system and up to $24,000 to connect to sewer. Who qualifies and how to apply.
Indian River County sewer connection grant and help
Indian River County has announced up to $15,000 per property to connect to sewer. Status, who qualifies, Vero Beach STEP help, SHIP repair money and payment options.
St. Lucie County septic and sewer help
Septic to sewer help in St. Lucie County: FPUA's $10,395 connection with financing, Port St. Lucie's 0% plan, North Hutchinson Island and SHIP repair money.